All of followings should be done by the project manager during project control except ( ).A. Determine that a change has occurredB. Ensure that a change is agreedC. Make sure all changes are approved by managementD. Manage changes as they occur
信管網(wǎng)參考答案:C(僅供參考,歡迎評(píng)論交流) 收藏