国产女主播一区二区|绝不放过你电影在线观看完整版|欧美寡妇性猛交ⅹxxx|谍战片电视剧免费观看电视剧大全在线观看,av片国产,国产精品欧美久久久久久,免费观看久久久

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學習 培訓課程
試卷名稱 信息系統(tǒng)項目管理師-pmp練習題-3
考試中心《信息系統(tǒng)項目管理師-pmp練習題-3》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

According to the project plan, the project should have been spent so far US$28,000, it represents US$28,000 per hour labor rate and works 1000 hours. Monitoring costs, the project manager determines that the cost performance index is 0.8. Actual project cost is US$40,000. What is the project's schedule variance?
A、–US$12,000
B、US$4,000
C、US$5,600
D、US$12,000


相關試題

推薦文章
合作網(wǎng)站內(nèi)容