国产女主播一区二区|绝不放过你电影在线观看完整版|欧美寡妇性猛交ⅹxxx|谍战片电视剧免费观看电视剧大全在线观看,av片国产,国产精品欧美久久久久久,免费观看久久久

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學習 培訓課程
試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(1)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(1)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

Towards the end of a large infrastructure project the tension rises, and conflicts between team members occur more frequently. This affects the productivity of the team, and takes the focus away from completing the scope. To restore order the project manager putts two people off the team and replaces them with others.What strategy does the project manager use?
A、Forcing
B、Avoiding
C、Compromising
D、Exchanging